Title: Contract - Long Foundation Drilling Co. - Transmission Pole Foundation City Council is requested to award a contract to Long Foundation Drilling Company in the amount of $322,276 to relocate a portion of 100kV transmission poles to accommodate the substation rehabilitation work at Jackson Lake Substation.
Attachments: 1. Contract – Long Foundation Drilling Co. – Transmission Pole Foundation

Title

Contract - Long Foundation Drilling Co. - Transmission Pole Foundation

City Council is requested to award a contract to Long Foundation Drilling Company in the amount of $322,276 to relocate a portion of 100kV transmission poles to accommodate the substation rehabilitation work at Jackson Lake Substation.