Amendment to Contract - Tanglebrook Sanitary Sewer Outfall Change Order #4
Council is requested to approve change order #4 to the Buckeye Bridge LLC contract in the amount of $10,065.00 and extend the completion date an additional 51 calendar days. This change order is required due to actual ground elevations differing from aerial survey elevations, resulting in a manhole being required that no unit pricing was provided for in the original contract.
|