File #: 2018-167    Version: 1 Name:
Type: Contract Status: Approved
File created: 5/15/2018 In control: City Council
On agenda: 5/21/2018 Final action: 5/21/2018
Title: Change Order to Contract - Wharton-Smith, Inc. - Eastside WWTP City Council is requested to approve a change order in the amount of $107,721.67 to the Wharton-Smith, Inc. contract to provide for additional repairs and replacement of equipment needed for the Eastside Wastewater Treatment Plant Solids Handling Improvements.
Sponsors: Committee of the Whole
Attachments: 1. 5. Change Order - Wharton-Smith Eastside WWTP Improvements

Title

Change Order to Contract - Wharton-Smith, Inc. - Eastside WWTP

City Council is requested to approve a change order in the amount of $107,721.67 to the Wharton-Smith, Inc. contract to provide for additional repairs and replacement of equipment needed for the Eastside Wastewater Treatment Plant Solids Handling Improvements.

Body

[Enter body here.]