Title:
|
Contracts - Equipment for the New Hammer Substation, Oak Hollow Substation and Burton Substation
Council is requested to approve contracts for the purchase of equipment and transformers for the New Hammer (Street) Substation, Oak Hollow and Burton (Road) Substations:
Schedule I - Substation Structure (Bldg.)Substation Enterprises $89,808.00
Schedule III - 15kV Circuit Breakers Siemens Industries $37,575.00
Schedule IV - Metalclad Switchgear AZZ, Inc. $444,254.00
Schedule V - Power Transformers (3) OTC Services, Inc. $1,960,767.00
|